Dodges Ferry Primary School will undergo a major redevelopment to provide additional contemporary learning environments, associated support spaces and amenities.
Aerial photo of Dodges Ferry Primary School
Timeline
The project initiation stage sees the commencement of project planning, documentation and engagement with the school community.
The initial stage of community engagement informs the development of a site concept plan.
Consultation is now closed.
This phase will see the development of a concept plan for the works.
The second stage of engagement provides opportunity for the community to review the concept plan via this website and other channels.
Community engagement (2nd stage) will commence in 2025.
Design development of the approved concept plan in readiness for tendering and construction.
This is expected to be completed in the second half of 2025.
Construction is expected to commence in 2026.
Construction is expected to be completed in 2028.