The Tasmanian Government is investing in new and upgraded education infrastructure.
Sorell School will undergo a major redevelopment, delivering a combination of new buildings and refurbishment of existing facilities, including a new Child and Family Learning Centre.
Construction commenced in September 2021 and will be completed in 2024.
Works are being staged to ensure the school can continue to operate and temporary changes are in place onsite to ensure the safety of students, staff and visitors.
Download the Sorell School Construction Staging map
Timeline
The initial stage of community engagement informs project initiation and concept master plan development – and was completed in March 2019.
Click here to view the Community Engagement Phase 1 Outcomes Report.
Community engagement is now closed.
Development of a concept master plan was completed in the second half of 2019.
Click to view the concept master plan.
This second stage of engagement provides opportunity for the community to review the concept master plan via this website and other channels.
Phase 2 of community engagement was completed in November 2019.
Click here to view the Community Engagement Phase 2 Outcomes Report.
Community engagement is now closed.
Construction commenced in September 2021.
Temporary arrangements are in place onsite to ensure the safety of students, staff and visitors to the school.
Download the Sorell School Construction Staging map